Site diary · Basement villa (B+G+1+R)

Build log: our featured villa project in Dubai.

One basement villa, stage by stage, from the empty plot to the latest pour, with photos from the site. For the trades behind it, see villa civil and finishing works in Dubai.

  1. Wellpoint trenches and pumps around the pit, on our featured villa project in Dubai (build log update 4).
    Update 4 · 21 Nov 2026

    Keeping the water out

    Wellpoints and pumps hold the groundwater below the dig.

  2. Digging and panelling at the same time, on our featured villa project in Dubai (build log update 3).
    Update 3 · 20 Nov 2026

    Going down: bulk excavation

    Sand out by the truckload, panels in as the dig gets deeper.

  3. Overview: excavators, panels and site cabins, on our featured villa project in Dubai (build log update 2).
    Update 2 · 16 Nov 2026

    Shoring goes in, the dig begins

    Steel beams around the plot, then precast panels as we go down.

  4. The empty plot, day one, on our featured villa project in Dubai (build log update 1).
    Update 1 · 13 Nov 2026

    Day one: an empty plot

    Hoarding up, gate in, site set up for a basement villa.