Site update 3

Going down: bulk excavation

Digging and panelling at the same time, on our featured villa project in Dubai (build log update 3).
Digging and panelling at the same time.

How much sand comes out of a villa basement? A lot.

This stage was all digging. Excavators worked across the plot while the panel wall followed them down, with edge protection along the top and trucks taking the sand away.

Bulk excavation is the stage where the basement takes its shape. The excavators work level by level across the plot, loading the sand straight onto trucks so it leaves site the same day instead of piling up around the edges and loading the shoring.

As each level comes out, the next row of panels goes in behind it, and edge protection goes up along the top of the cut so nobody can fall into the dig. By the end of this stage there was a long shored corridor around the walls and an open pit in the middle of the plot.

Why it matters

Excavation and shoring move together: dig a level, panel it, dig the next. The survey and level checks run alongside so the bottom ends up exactly where the drawings say.

Our crews on this stage

See the villa civil and finishing works our crews carry out in Dubai.

On site

What comes next

Site update 4: Keeping the water out. Wellpoints and pumps hold the groundwater below the dig.