Site update 5
Bottom of the dig

This is what 'ready to build' looks like underground.
With the dig at full depth, the floor was levelled and compacted, road base spread, and the surveyor marked out every footing. The lift and sump pits are next.
Formation level is the depth the drawings say the building sits on. Getting there isn't just digging until the number is reached: the last layer is trimmed, levelled and compacted in layers so the ground under the raft is firm and even, and the compaction is tested before anything is built on it.
Then the surveyor takes over. Grid lines, footing outlines and pit positions are set out on the compacted base, so every wall, column and pit from here on is built from the same points. While the floor was being rolled, the dewatering pipes kept working around the edges.
Why it matters
Compaction tests and setting out look small on a photo, but every wall, column and pit after this point is built off these lines.
Our crews on this stage
See the villa civil and finishing works our crews carry out in Dubai.
On site




What comes next
Site update 6: Pits for the lift and sump, coming soon. Digging the deeper pockets, then compacting their bases.